A FirstEnergy affiliate, American Transmission Systems Inc., is proposing to install one new transmission structure on the Inland-Harding (S-8) 345-kV transmission line approximately 30 feet to the northeast of existing Structure #15517. The Project is located in the city of Cleveland, Cuyahoga County, Ohio.

Project Documents

A paper copy of the application can be supplied within 5 business days upon request at no more than the cost or printing and shipping. Request for a paper copy can be made by contacting the transmission project hotline at 1-800-589-2837 or by email. The project name and Case Number (17-1571-EL-BNR) should be referenced in all communications.