Chamberlin Substation 138kV Strain Bus Structure Addition Project, OPSB Case No. 20-1710-EL-BNR

In this project, ATSI will construct a 138-kV strain bus tie at the Chamberlin Substation to connect the existing 138-kV substation yard to a new 345/138 kV transformer installed within the existing 345-kV substation yard. To construct the 138 kV strain bus, one new single steel monopole on concrete foundation will be installed outside the existing substation fence. Approximately 550 feet of new 1590 kcmil 45/7 ACSR bundle conductor will be installed between 138-kV and 345-kV yards of Chamberlin Substation. The project is located in Twinsburg Township, Summit County, Ohio.

Project Documents

A paper copy of the application can be supplied within 5 business days upon request at no more than the cost or printing and shipping. Request for a paper copy can be made by contacting the transmission project hotline at  1-800-589-2837 or by email. The project name and Case Number (20-1710-EL-BNR) should be referenced in all communications.