In this Project, ATSI proposes to reconfigure a 138 kV transmission line connection to the existing Ashtabula East Substation. ATSI will:

  • Modify four existing structures: Structure #12688, Structure #12467 and Structure #12468 on the existing Ashtabula East-Ashtabula 138 kV Transmission Line and Structure #12469 on the existing Ashtabula-Pittsconn Docks 138 kV Q15 Transmission Line. The existing switch (A301) on Structure #12467 will be removed as part of this Project.
  • Install five new structures: two (2) new switch structures (Structures #2 and #3A), one (1) tap structure (Structure #3), and two (2) single circuit deadend structures on concrete foundations (Structures #1 and #4). Approximately 4,300 linear feet of 336.4 kcmil 26/7 ACSR new conductor (for three phases of conductor) will be installed.
  • Remove existing Structures #12686 and #12687 and the associated transmission line conductor.

The Project is in Ashtabula Township, Ashtabula County, Ohio.
 

Project Documents

A paper copy of the application can be supplied within five business days upon request at no more than the cost of printing and shipping. Request for a paper copy can be made by contacting the transmission project hotline at 1-888-311-4737 or by email. Please reference the project name and case number (26-0010-EL-BNR) in all communications.