A FirstEnergy affiliate, American Transmission Systems Inc., is proposing to replace two existing wood pole tangent structures with two new single circuit wood pole 3-way deadend structures on the Bayshore-GM Powertrain 138-kV transmission line and GM Powertrain-Jackman 138-kV transmission line leading to the customer owned GM Powertrain Substation. One temporary single circuit wood pole structure will also be installed for a temporary 138-kV transmission connection, approximately 60 – 90 feet in length, to a mobile transformer that will be installed at the GM Powertrain Substation during this project’s construction. This project is being proposed to accommodate upgrades to the substation.

Project Documents

A paper copy of the application can be supplied within 5 business days upon request at no more than the cost or printing and shipping. Request for a paper copy can be made by contacting the transmission project hotline at 1-800-589-2837 or by email. The project name and Case Number (17-1241-EL-BNR) should be referenced in all communications.