East Springfield-London #2 138-kV Transmission Line Extensions to North Titus Substation Project (Case No. 18-0086-EL-BLN)

A FirstEnergy affiliate, American Transmission Systems Inc. is proposing to construct two separate transmission line segments from the East Springfield-London #2 138-kV transmission line to the new North Titus Substation. These lines will be an approximately 1.0-mile-long East Springfield-North Titus 138-kV Transmission Line and an approximately 0.6-mile-long London-North Titus 138-kV Transmission Line. The Project is needed for Silfex Inc.’s (“Silfex”) new manufacturing facility located in the City of Springfield, Clark County, Ohio.

Project Documents

A paper copy of the application can be supplied within 5 business days upon request at no more than the cost or printing and shipping. Request for a paper copy can be made by contacting the transmission project hotline at 1-800-589-2837 or by email. The project name and Case Number (18-0086-EL-BLN) should be referenced in all communications.

Last Modified: May 8, 2018