Procedure to interconnect small generation with the FirstEnergy Distribution System
Pennsylvania - Metropolitan Edison Company (Met-Ed), Pennsylvania Electric Company (Penelec), Pennsylvania Power Company (Penn Power)
Prior to completing the application process, a customer interested in interconnecting small generation with the FirstEnergy distribution system must first determine the size and type of equipment to install.
NOTE: For a residential customer, the limit is 50kW. For all others, the limit is 3000kW (up to 5000kW under certain conditions). See the Pennsylvania Public Utility Commission’s Web site for Regulations for Interconnection Standards at 52 Pa. Code §75.21 et seq., http://www.puc.state.pa.us/PcDocs/630340.doc
Application Process
| 1. |
Customer Application Checklist |
|
- Submit Completed
- Submit Site Plan
(Site Plan Example (pdf))
- Submit One-line diagram
(PV Example (pdf), Turbine Example (pdf))
- Submit Application Fee
- Met-Ed/Penelec – photovoltaic (PV) - $100
- Met-Ed/Penelec – All Others (Wind, Hydro, etc.) - $300
- Penn Power - Actual costs
- Submit completed documents to
- FirstEnergy Corp.
c/o Metropolitan Edison Company P.O. Box 16001 Reading, PA 19640 Attn: PA Rates – Net Metering & Interconnection OR
- E-mail feinterconnection@firstenergycorp.com OR
- Fax: (330) 777-6188
(Please use highest resolution setting on Fax machine) |
| 2. |
Company Review |
|
After review by the Company, the customer will be notified if the application is approved or if there are any deficiencies. The customer must correct any deficiencies before the Company will approve the facility for installation. |
| 3. |
Following approval of the application, the customer installs the facility in accordance with the Application. |
| 4. |
Following installation, the Customer submits final documents |
|
- Submit completed
- Submit evidence of Electrical Inspection by authorized inspection agency
- Submit Net Energy Metering Rider Application (doc)
(if applicable per PA Regulations). See the Pennsylvania Public Utility Commission's Web site for Regulations for Net Metering at 52 Pa. Code §75.11 et seq., http://www.puc.state.pa.us/PcDocs/568424.doc
- Submit completed documents via same method as Step 1 above
|
| 5. |
Final Steps by Company |
|
- Review and approve the as-built installation and final documentation
- Determine the need for a witness test as provided for in the regulations and notify customer
- Finalize documentation and authorize system operation
- Arrange for the installation of net energy metering, where appropriate
|
Questions
Technical and policy questions regarding interconnection issues should be directed to feinterconnection@firstenergycorp.com or FirstEnergy Corp., c/o Metropolitan Edison Company, P.O. Box 16001, Reading, PA 19640, Attn: PA Rates – Net Metering & Interconnection.
General metering and billing questions should be directed to Customer Service at 1-800-545-7741.